Which of the following describes the LOWEST level of a work breakdown structure (WBS)?

Which of the following describes the LOWEST level of a work breakdown structure (WBS)?

Which of the following describes the LOWEST level of a work breakdown structure (WBS)?

A.
Technical specifications

B.
Project performance reports

C.
Work packages

D.
Functional specifications