Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?

Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?

Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?

A.
Request for Proposal (RFP)

B.
Quality management plan

C.
Change control board

D.
Version control system