In an attempt to make a deadline, a North American project manager is able to procure emergency
funding for additional people. The resources are located in Europe. Which of the following project
components will have to be updated to reflect working with a new time zone location?
A.
Communication plan
B.
Risk management plan
C.
Work Breakdown Structure (WBS)
D.
Project scope statement
Explanation:
The communication plan is the first document that needs to be updated. Work
Breakdown structure or WBS only documents the work process. First thing is to set up a
communication plan