Which of the following is BEST suited in this situation to show the activities’ logical relationship?

The project manager is sequencing a set of activities. They discover that some of the
activities may or may not occur based on the outcome of other activities. Which of the
following is BEST suited in this situation to show the activities’ logical relationship?

The project manager is sequencing a set of activities. They discover that some of the
activities may or may not occur based on the outcome of other activities. Which of the
following is BEST suited in this situation to show the activities’ logical relationship?

A.
Gantt

B.
CCM

C.
ADM

D.
CCB