A project manager has decided to increase the member of resources working on critical path
activities. This is an example of:
A.
rolling wave planning.
B.
resource leveling
C.
fast tracking.
D.
crashing.
A project manager has decided to increase the member of resources working on critical path
activities. This is an example of:
A project manager has decided to increase the member of resources working on critical path
activities. This is an example of:
A.
rolling wave planning.
B.
resource leveling
C.
fast tracking.
D.
crashing.
Shouldn’t that be C)?