This is an example of:

A project manager has decided to increase the member of resources working on critical path
activities. This is an example of:

A project manager has decided to increase the member of resources working on critical path
activities. This is an example of:

A.
rolling wave planning.

B.
resource leveling

C.
fast tracking.

D.
crashing.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Craig

Craig

Shouldn’t that be C)?