Given the following information:
Pessimistic estimate is 30 days
Most Likely estimate is 15 days
Optimistic estimate Is 10 days
Which of the following is the expected duration for this scheduled activity?
A.
11 days
B.
17 days
C.
25 days
D.
29 days