Who has the MOST control over project scope changes?
A.
Key stakeholders
B.
Project sponsor
C.
Project manager
D.
Change control board
Who has the MOST control over project scope changes?
Who has the MOST control over project scope changes?
A.
Key stakeholders
B.
Project sponsor
C.
Project manager
D.
Change control board
The correct answer is D. The project manager may convene and participate in the CCB, but the board as a whole clears or rejects and changes to the project scope (at least during the Executing phase). We are assuming that the scope has been signed off on by the sponsor and the project is executing.