The amount of time ahead or behind schedule on a project is called the:

The amount of time ahead or behind schedule on a project is called the:

The amount of time ahead or behind schedule on a project is called the:

A.
schedule baseline.

B.
schedule performance index.

C.
estimated to complete.

D.
scheduled variance.



Leave a Reply 2

Your email address will not be published. Required fields are marked *


MrIntel

MrIntel

The correct answer is D.