The amount of time ahead or behind schedule on a project is called the:
A.
schedule baseline.
B.
schedule performance index.
C.
estimated to complete.
D.
scheduled variance.
The amount of time ahead or behind schedule on a project is called the:
The amount of time ahead or behind schedule on a project is called the:
A.
schedule baseline.
B.
schedule performance index.
C.
estimated to complete.
D.
scheduled variance.
Answer is D.
The correct answer is D.