All of the following are considered part of the risk management plan EXCEPT the risk:
A.
register,
B.
matrix,
C.
assessment
D.
baseline,
All of the following are considered part of the risk management plan EXCEPT the risk:
All of the following are considered part of the risk management plan EXCEPT the risk:
A.
register,
B.
matrix,
C.
assessment
D.
baseline,
Admin: D is the correct answer
2.8 Outline the components of a risk management plan
• Initial risk assessment
• Risk matrix
• Risk register
• Risk response strategies
The correct answer is D.