When ensuring the quality of project deliverables, which of the following is the NEXT step the
project manager should take, once performance information has been gathered?
A.
Create Gantt charts
B.
Generate change requests
C.
Identify variances
D.
Implement change requests
Admin: Answer is C.
The correct answer is C. Gantt charts are for project scheduling, not quality.