The project kick-off meeting is held:
A.
at the end of the planning process.
B.
before getting a signed project charter.
C.
during the initiating process.
D.
after the post review meeting.
The project kick-off meeting is held:
The project kick-off meeting is held:
A.
at the end of the planning process.
B.
before getting a signed project charter.
C.
during the initiating process.
D.
after the post review meeting.
The correct answer is A. The kickoff meeting is held after the planning phase to formally “kick off” the executing phase.