A stakeholder asks the project manager to finish a project early. The project manager should ask
the stakeholder to FIRST:
A.
Speak to the other stakeholders to get their opinion.
B.
Complete a change request form.
C.
Speak to the project sponsor.
D.
Consider how this might Impact the quality of the product.
The correct answer is B. A stakeholder needs to formally submit the change request in writing before considering the impact.
The correct answer is B.