Which of the following is the FINAL step in the pre-project setup phase?
A.
Obtain signed approval of the project charter.
B.
Obtain signed approval of the statement of work (SOW).
C.
Conduct a feasibility analysis for the project.
D.
Create the work breakdown structure (WBS).
Explanation:
Topic 3, Volume C