which of the following is the CV for the project?

If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

A.
-$1,000

B.
$1,000

C.
-$3,000

D.
$3,000



Leave a Reply 0

Your email address will not be published. Required fields are marked *