A manager and the head of engineering discuss a change to a major work package. After the
meeting, the project manager contacts a third person and tells them to complete the paperwork to
make the change. Who did the project manager contact?
A.
A project sponsor
B.
A third party vendor
C.
A change control board member
D.
A project expediter