Which of the following is the correct formula for computing a project SPI?

Which of the following is the correct formula for computing a project SPI?

Which of the following is the correct formula for computing a project SPI?

A.
SPI = EV-AC

B.
SPI = EV/PV

C.
SPI = EV-PV

D.
SPI = EV/AC