Which of the following would be the BEST tool to estimate activity time durations?

Which of the following would be the BEST tool to estimate activity time durations?

Which of the following would be the BEST tool to estimate activity time durations?

A.
Gantt chart

B.
CPM

C.
Estimating model

D.
PERT



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Michael McNeil

Michael McNeil

Admin: I believe D would be the best answer.

CPM is for a whole project, where PERT can be used for an individual activity.