During handover stage a customer of a particular project noticed the extended warranty from a
particular vendor for a critical application has not been ordered. In which of the following
documents should this have been previously addressed?
A.
Procurement management plan
B.
Project charter
C.
Staffing management plan
D.
Risk management plan