A project manager is performing activity duration estimation. This project will have conditional
decisions. Which of the following tools would be the BEST to use?
A.
GERT
B.
Gantt chart
C.
PERT
D.
EVM
A project manager is performing activity duration estimation. This project will have conditional
decisions. Which of the following tools would be the BEST to use?
A project manager is performing activity duration estimation. This project will have conditional
decisions. Which of the following tools would be the BEST to use?
A.
GERT
B.
Gantt chart
C.
PERT
D.
EVM
Gantt charts are used to gauge a project schedule
http://en.wikipedia.org/wiki/Gantt_chart
It is PERT, hence the reference to ‘conditional decisions’ in the question. Ie: dependencies
http://www.inc.com/encyclopedia/program-evaluation-and-review-technique-pert.html