A project manager has failed to obtain the necessary permits from the local building commission.
The project has been stopped because of a failure to understand the importance of:
A.
internal process compliance.
B.
risk avoidance.
C.
standards compliance.
D.
audit trail compliance.
Admin: I’m thinking an issue concerning permits is not a risk thing but is closer to a standard compliance. So the answer should be B.
The correct answer is C.