which of the following performance statistics?

A variance between the planned scheduled work and the actual work completed would initially be
highlighted in which of the following performance statistics?

A variance between the planned scheduled work and the actual work completed would initially be
highlighted in which of the following performance statistics?

A.
CV

B.
SV

C.
CPI

D.
ETC



Leave a Reply 2

Your email address will not be published. Required fields are marked *


Michael McNeil

Michael McNeil

Admin: I’m thinking A is correct.

steve

steve

I would say B.