Which of the following is the correct progression of the project life cycle?
A.
Planning, Initiating, executing, monitoring / controlling, closing
B.
Initiating, planning, executing, monitoring / controlling, closing
C.
Planning, Initiating, monitoring / controlling, executing, closing
D.
Initiating, planning, monitoring / controlling, executing, closing
ADMIN, please fix. The Correct Answer is B.
Outline the process groups of the project life cycle
• Initiating/Pre-Project Setup
• Planning
• Executing
• Monitoring/controlling
• Closing