Which of the following is a characteristic of a project charter?
A.
Issued by the project manager with support from the project sponsor.
B.
Links the project to the on-going work of the organization through a business plan.
C.
Formally recognizes the existence or establishment of the project.
D.
Provides low-level requirements for the project.