Which of the following is created using the work breakdown structure (WBS) as an input?
A.
Procurement management plan
B.
Vendor selection criteria
C.
Project scope statement
D.
Project charter
Which of the following is created using the work breakdown structure (WBS) as an input?
Which of the following is created using the work breakdown structure (WBS) as an input?
A.
Procurement management plan
B.
Vendor selection criteria
C.
Project scope statement
D.
Project charter
Here’s a chicken before the egg thing.
First the Project Scope Statement inputs into the WBS and then the WBS inputs into the Project Scope Statement updates.