Which of the following should the project manager do to gather this information?

A project manager needs to determine how much it will cost for a third party to complete certain
deliverables and the steps they will take to complete those deliverables. Which of the following
should the project manager do to gather this information?

A project manager needs to determine how much it will cost for a third party to complete certain
deliverables and the steps they will take to complete those deliverables. Which of the following
should the project manager do to gather this information?

A.
Issue a RFQ

B.
Issue an RFP

C.
Create a WBS

D.
Develop a SOW

Explanation: