Which of the following describes crashing a project schedule?
A.
Project activities that would normally be completed in sequence are performed concurrently.
B.
Additional resources are deployed.
C.
All float time is removed from the project schedule.
D.
The project manager reviews the project scope to determine unnecessary requirements.
Explanation: