which of the following risk response techniques to resolve the issue?

An important team member will not be available to complete a project. The project manager
selects a new team member and trains the new team member on the project tasks. The project
manager is using which of the following risk response techniques to resolve the issue?

An important team member will not be available to complete a project. The project manager
selects a new team member and trains the new team member on the project tasks. The project
manager is using which of the following risk response techniques to resolve the issue?

A.
Monitor the risk

B.
Mitigation of the risk

C.
Acceptance of the risk

D.
Transference of the risk

Explanation: