A project has produced 2000 of the same deliverable. The project manager does not have time to
inspect every deliverable, but would like some assurance the deliverables are meeting the
specifications. Which of the following techniques should be used?
A.
Defect repair review
B.
Process analysis
C.
Statistical sampling
D.
Design of experiments