A project manager is finding that stakeholders are not up-to-date on the project status. When
determining how to correct the problem, the project manager should FIRST review which of the
following documents?
A.
Responsibility matrix
B.
Statement of Work (SOW)
C.
Issue log
D.
Communications plan