Which of the following shows a project that is presently over its financial budget?

Which of the following shows a project that is presently over its financial budget?

Which of the following shows a project that is presently over its financial budget?

A.
CPI = 1.4

B.
CPI = 0

C.
CV = +$11,000

D.
CPI = 0.8



Leave a Reply 7

Your email address will not be published. Required fields are marked *


Michael McNeil

Michael McNeil

Admin: The correct answer is C.

Cost Variance %

Cost Variance % indicates how much over or under budget the project is in terms of percentage.

Cost Variance % can be calculated using the following formula:

CV % = Cost Variance (CV) / Earned Value (EV)

OR

CV % = CV / BCWP

The formula mentioned above gives the variance in terms of percentage which will indicate how much less or more money has been used to complete the work as planned in terms of percentage.

Positive Variance % indicates % under Budget.

Negative Variance % indicates % over Budget.

Michael McNeil

Michael McNeil

Cost Performance Indicator (CPI)

Cost Performance Indicator is an index showing the efficiency of the utilization of the resources on the project. Cost Performance Indicator can be calculated using the following formula:

CPI = Earned Value (EV) / Actual Cost (AC)

OR

CPI = BCWP / ACWP

The formula mentioned above gives the efficiency of the utilization of the resources allocated to the project.

CPI value above 1 indicates efficiency in utilizing the resources allocated to the project is good.

CPI value below 1 indicates efficiency in utilizing the resources allocated to the project is not good.

Michael McNeil

Michael McNeil

Cost Variance (CV) is a very important factor to measure project performance. Cost Variance (CV) indicates how much over or under budget the project is.

Cost Variance can be calculated using the following formula:

Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC)

OR

Cost Variance (CV) = BCWP – ACWP

The formula mentioned above gives the variance in terms of cost which will indicate how less or more cost has been used to complete the work as of date.

Positive Cost Variance Indicates the project is under budget.

Negative Cost Variance Indicates the project is over budget

Michael McNeil

Michael McNeil

Admin: Second thought, none of the answers work. Please fix.

Andrei G.

Andrei G.

The correct answer is D! Because having a lower than 1 CPI negatively affects the EAC (estimate at completion).

EAC=BAC/CPI

If BAC=$10000 and CPI=0.8 then EAC=$12500; $2500 more than planed.

Hence you are over budget!

2LTech

2LTech

The answer is D

Angela Ant

Angela Ant

Passed my PK0-003 exam last week, scored 850/900! I had 95 total multiple choice questions, and I learned most of them from this valid dumps — http://www.passleader.com/pk0-003.html, useful and helpful when I prepared for the PK0-003 exam. p.s. The PK0-003 exam is very difficult for passing, I think one premium braindump can help you passing exam easily! Good Luck.