A project manager has decided to reduce the impact of a possible threat. Which of the following
risk response strategies BEST describes this action?
A.
Avoidance
B.
Exploiting
C.
Mitigation
D.
Acceptance
Explanation:
A project manager has decided to reduce the impact of a possible threat. Which of the following
risk response strategies BEST describes this action?
A project manager has decided to reduce the impact of a possible threat. Which of the following
risk response strategies BEST describes this action?
A.
Avoidance
B.
Exploiting
C.
Mitigation
D.
Acceptance
Explanation: