A project team member has identified a required change to one of their assigned tasks. The
change would alter the order in which other tasks must be completed. Which of the following
should be done NEXT?
A.
Perform an impact analysis
B. Implement the change
C.
Update the change registry
D.
Document the change
I believe the answer is A
I believe this is D.
This is the order I have:
-Assign a request
-record in change log
Impact analysis
-submit request
(approved or not)
-inform stake holder of decision
The CompTIA Project+ PK0-003 exam will be retired on 9/30/2017! Now, the new CompTIA Project+ PK0-004 dumps are available, part of NEW PK0-004 exam questions for your reference:
NEW QUESTION 1
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation. Which of-the following should the project manager bring to the meeting to support this recommendation? (Select TWO.)
A. The issue log to show why the vendor should be replaced
B. The team action items to show why the vendor should be replaced
C. The scope statement to show why the vendor should be replaced
D. A procurement plan to show why the vendor should be replaced
E. A change management plan to have the vendor replaced
Answer: AE
NEW QUESTION 2
A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low high bids must be rejected to determine the selected vendor. Which of the following terms describes this requirement?
A. Outsourcing
B. Business acquisition
C. Business process change
D. Internal reorganization
Answer: A
NEW QUESTION 3
The project manager has noticed a vendor is not performing in accordance with the SLA Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?
A. Balanced score card
B. WBS
C. Post-project evaluation
D. PERT
Answer: B
NEW QUESTION 4
Team members have reported that meetings are poorly attended and unproductive Which of the following steps can the project manager take to make the meetings more productive?
A. Discontinue the meetings with the poorest attendance.
B. Decrease the length of the meetings.
C. Distribute an agenda before each meeting.
D. Document team member attendance and report it to management.
Answer: D
NEW QUESTION 5
Which of the following documents should be used to provide high-level reporting to key stakeholders?
A. Dashboard
B. Communication plan
C. Statement of work
D. Project charter
Answer: C
NEW QUESTION 6
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the fallowing documents would contain these items?
A. Business case
B. Requirements document
C. Project timeline
D. Task plan
Answer: A
NEW QUESTION 7
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close-date The project team meets and determines that the project should be fast-tracked Which of the following documents should the project team reference to fast-track the project? (Select TWO.)
A. Scope management plan
B. Configuration management plan
C. Network diagram
D. Project schedule
E. Project plan
Answer: AC
NEW QUESTION 8
……
P.S. Get The Newest PK0-004 Dumps In PDF And VCE From — http://www.passleader.com/pk0-004.html (115q VCE and PDF)
Good Luck!
BTW, part of that new 115Q PK0-004 dumps are available here:
https://drive.google.com/open?id=0B-ob6L_QjGLpWmFpamxGZTNmX0U
Best Regards!
The English Version PK0-003 Exam Has Retired, New Exam Code is PK0-004 Now!
I just cleared the PK0-004 exam last week with a good score of 8xx/900 (the passing score is 710/900 now).
I had 95 questions (~~~Maximum Qs~~~LOL~~~).
MCQs and fill in the blank questions.
Around 30% questions are about Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.
Also, many questions on Communication and Change Management (about 20%).
Pay close attention to the subject of “Project Tools & Documentation”, a little difficult, I lost points in this section. (~~~LOL~~~)
Questions on this site are sure not enough for passing!
Recommend to learn the PassLeader PK0-004 dumps, all questions are from it.
Here you can review the PL PK0-004 dumps for free:
http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps
Good Luck!