Which of the following is the project manager implementing when they allocate…?

Which of the following is the project manager implementing when they allocate additional

resources to a set of tasks that are in the critical path and are slowing down the project
completion?

Which of the following is the project manager implementing when they allocate additional

resources to a set of tasks that are in the critical path and are slowing down the project
completion?

A.
Crashing

B.
Optimizing

C.
Controlling

D.
Fast tracking