Which of the following scheduling algorithms establishes floats, durations, and paths between work schedule activities?

Which of the following scheduling algorithms establishes floats, durations, and paths
between work schedule activities?

Which of the following scheduling algorithms establishes floats, durations, and paths
between work schedule activities?

A.
AON

B.
PERT

C.
CPM

D.
GERT