Which of the following should be ADDED to the risk tracking sheet?

A draft structure for a risk tracking sheet has been provided below: – Risk identifier. – Risk
status. – Risk description. – Mitigation steps. – Mitigation status. Which of the following
should be ADDED to the risk tracking sheet?

A draft structure for a risk tracking sheet has been provided below: – Risk identifier. – Risk
status. – Risk description. – Mitigation steps. – Mitigation status. Which of the following
should be ADDED to the risk tracking sheet?

A.
Risk matrix

B.
Risk rating

C.
Stakeholder risk tolerance

D.
Revised project schedule

Explanation: