A key supplier has informed the project manager that there will be a two month delay to
fulfill an order. Which component of the project plan is affected and which of the following
actions should be taken?
A.
Manage scope and consider a project change request.
B.
Evaluate the project schedule and raise a project issue.
C.
Manage project quality and schedule a meeting.
D.
Implement approved changes by utilizing a change management form.