Which of the following is indicative of a ‘finish-to-start’ direct relationship in a project
schedule?
A.
Activity A must begin before Activity B can end.
B.
Activity A must begin before Activity B can begin.
C.
Activity A must end before Activity B can end.
D.
Activity A must end before Activity B can begin.