The project manager of a project that involves a system-wide computer update receives a
report that some computers cannot be updated. Which of the following is a BEST practice?
A.
Perform an impact analysis and contact the project sponsor.
B.
Document the change to the project without informing the stakeholders.
C.
Contact the stakeholders in the project to determine the best course of action.
D. Complete a project management change form without notifying the sponsor.