Which of the following would be the FIRST action that should be taken to obtain the custom part?

An equipment reseller with limited manufacturing capacity is introducing a new product line
that requires a custom fabricated part. Which of the following would be the FIRST action
that should be taken to obtain the custom part?

An equipment reseller with limited manufacturing capacity is introducing a new product line
that requires a custom fabricated part. Which of the following would be the FIRST action
that should be taken to obtain the custom part?

A.
Perform a make or buy analysis

B.
Create an RFP to be sent out to current product vendors

C.
Develop detailed drawings and submit to manufacturing for production

D.
Submit an RFI to a local manufacturing facility

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *