A project with a projected budget of $100,000 is 75% complete and has a CPI of .85. Which
of the following is TRUE regarding this project?
A.
More project work than projected has been completed
B.
The project is currently in cost overrun
C.
The project EV is 63.75
D.
$85,000 has been spent in the project
Explanation: