Which of the following actions should the project manager take?

The business stakeholder has been engaged late and has just had a chance to review the
approved requirements. Consequently, it has been identified that there are a number of
gaps in the requirements which are critical to the stakeholder’s business unit. Which of the
following actions should the project manager take?

The business stakeholder has been engaged late and has just had a chance to review the
approved requirements. Consequently, it has been identified that there are a number of
gaps in the requirements which are critical to the stakeholder’s business unit. Which of the
following actions should the project manager take?

A.
Initiate change control

B.
Follow communications plan

C.
Manage project quality

D.
Prepare a performance report