Which of the following schedule compression techniques should be used by the project manager?

The project manager has had a large number of change requests approved by the project
steering committee, but has been given no extra time to deliver the project. Which of the
following schedule compression techniques should be used by the project manager?

The project manager has had a large number of change requests approved by the project
steering committee, but has been given no extra time to deliver the project. Which of the
following schedule compression techniques should be used by the project manager?

A.
Rebaselining

B.
Crashing

C.
Rescheduling

D.
Control scope

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *