Which of the following tools would a project manager use to determine the root cause of an issue?

Which of the following tools would a project manager use to determine the root cause of an
issue?

Which of the following tools would a project manager use to determine the root cause of an
issue?

A.
Pareto Chart

B.
Monte Carlo Analysis

C.
Histogram

D.
Ishikawa Diagram