A stakeholder wants to add another requirement to the deliverable. Which of the following
will the project manager do to determine the change’s effect on the project?
A.
 Filling out a change control
B.
 Performing an impact analysis
C.
 Identifying a change
D.
 Coordinating with stakeholders to select the course of action
Explanation: