Which of the following should be updated as a result?

While working on a project, an unforeseen event arises that impacts a project objective.
Which of the following should be updated as a result?

While working on a project, an unforeseen event arises that impacts a project objective.
Which of the following should be updated as a result?

A.
Stakeholder register

B.
Issue log

C.
Risk register

D.
Change log

Explanation: