The primary purpose for documenting lessons learned during project closure is to:
A.
Identify post project needs for functional teams.
B.
Report project deficiencies to the sponsor.
C.
Complete the post implementation/closeout report.
D.
Provide a historical resource for future projects of a similar nature.
Explanation: