A project’s Critical Path is:
A.
Asequence of activities that takes the shortest time to complete.
B.
Asequence of activities that takes the longest time to complete.
C.
Asequence of the activities that can be delayed without impacting the project’s end date.
D.
Asequence of the project’s activities required to meet the defined milestones.
Explanation: