Which of the following schedule planning techniques could be used to meet this request?

The project sponsor has asked for the project to be delivered two months earlier than
originally planned with no changes to the deliverables, cost, or the project team. Which of
the following schedule planning techniques could be used to meet this request?

The project sponsor has asked for the project to be delivered two months earlier than
originally planned with no changes to the deliverables, cost, or the project team. Which of
the following schedule planning techniques could be used to meet this request?

A.
Resource leveling

B.
Optimizing

C.
Crashing

D.
Delaying