Which of the following does the Critical Path tell the Project Manager?

Which of the following does the Critical Path tell the Project Manager? (Select TWO).

Which of the following does the Critical Path tell the Project Manager? (Select TWO).

A.
Where potential delays in the project might occur

B.
The earliest completion for project work

C.
Activities that can be done in parallel

D.
The allocation time for each person assigned to the project

E.
The longest series of activities



Leave a Reply 0

Your email address will not be published. Required fields are marked *

three × 2 =