Which of the following risk response planning techniques is a project manager using when
they are changing the project plan to remove the risks impact?
A.
Avoidance
B.
Transference
C.
Mitigation
D.
Acceptance
Explanation:
Which of the following risk response planning techniques is a project manager using when
they are changing the project plan to remove the risks impact?
Which of the following risk response planning techniques is a project manager using when
they are changing the project plan to remove the risks impact?
A.
Avoidance
B.
Transference
C.
Mitigation
D.
Acceptance
Explanation: